Successful start for the team of Konrad Pumpe GmbH! After a total of four "BIG Mix V" solids feeders with a capacity of 126m³ each were escorted to a biogas plant in Køng/Denmark at the beginning of the year, the commissioning of the last two BIG Mix V solids feeders took place at the beginning of last month.
After successful filling of the substrate, the starting signal was given for dosing in both plants. Without any problems, the material was transferred to a subsequent feeding system, which then conveyed the substrate into the fermenter of the biogas plant.
The commissioning was accompanied by two employees from our company. After completion of the second commissioning, the equipment of Konrad Pumpe GmbH is a functioning part of conveying components for a large biogas plant in Denmark.
We are happy about the smooth start and congratulate on this great biogas plant!